The NSW Government has committed $6.7 million for the initial development of the new synthetic athletics track at Sydney Academy of Sport, Narrabeen. The project will support users from grassroots to elite across a range of sports.
The project scope includes:
- A new World Athletics (WA) compliant synthetic athletics track with moisture resilient track surface
- New asphalt sub-base
- Drainage and stormwater system upgrades
- Accessibility improvements
The project timeline is:
- Planning: Commenced July 2025
- Design: December 2024 to October 2025
- Construction: November/December 2025 to September Quarter 2026
- Completion: September Quarter 2026
For detailed information please refer to the project website: https://www.sport.nsw.gov.au/capital-works-projects/sydney-academy-athletics-track